• HIGHLIGHTS April 5, 2018 Impact meeting on Water-Sewer Project on North Blvd

    Highlights from 4/5/18 Meeting on Water-Sewer Project on North Blvd:
     

    Project expected to start 2nd week of May 2018. Project to run May-November 2018.

     

    North Blvd work between Forest to Kenilworth. - Most invasive with portions of street closures, however detours and special access available as need be.  South and North Clinton will be most invasive with digging involved. Businesses please contact Business Engineer with concerns.

     

    South Blvd work will be NON-intrusive to Business and Homeowners.

     

    Water will NOT be shut off during ALL areas of work.  CTA/PACE services will be coordinating to continue regular service.

     

    Contracters have had been briefed on all Summer and Fall activities in Oak Park and will work to make work as less intrusive to the community as possible.

     

    For updates GO TO:

    https://www.oak-park.us/your-government/village-manager/village-managers-weekly-report

    Then to Boulevard Project.  Contact: 708.358.5700

     